TTI - Distribution Center Addition Phase 1

McCrory provided construction services for a distribution center expansion located on TTI’s ever-growing Anderson, South Carolina campus. The west expansion (300,000-square-feet) is constructed of load-bearing tilt-up wall panels with high bays for additional rack storage. The floor is a Ductilcrete system designed specifically for warehousing and distribution facilities.

This expansion was constructed during the height of the shipping season. McCrory worked closely with facility personnel to minimize interruptions to traffic flow and daily facility operations. 

“McCrory provided a Team of qualified subcontractors with the expertise and resources required to deliver this project successfully.”

Director of Greenville Operations
  • 300,000-square-foot warehouse expansion

  • Load-bearing tilt-up wall panels

  • Ductilcrete floor slab designed for distribution facilities

  • On-going facility operations during construction

  • Maintained perimeter ring road at all times

  • Project was delivered ahead of schedule by utilizing temporary heating measures to place floor slabs during winter months